Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Browsing all 3204 articles
Browse latest View live

Answered: NEC ECC: Is a PMI always a Compensation Event?

Examples of PMIs which are not compensation events : - an instruction to attend an early warning meeting (clause 16.2 of NEC3 ECC) - an instruction to remove a person (clause 24.2 of NEC3 ECC) - an...

View Article


Answered: NEC ECC: Change to working pattern

No this is not the same thing as acceleration, which is specifically dealt with under clause 36 of the contract. This instruction would be a compensation event which would be assessed accordingly...

View Article


NEC ECC: Can contractor claim for loss of profit under Option B, if so,...

The priced contract value is turning out to be 50% more than the actual value. Quantities were overstated and the Contractor mobilised based on false quantities.

View Article

Answered: NEC ECC: Is a PMI always a Compensation Event?

No a PMI is not a compensation event in its own right. If a Project Manager is instructing something that they know IS a compensation event, then at the time of giving the instruction they should state...

View Article

NEC ECC: Project manager not supplying all the information to complete the...

A PC amount of 2000.00 was allowed for in the original BOQ for signage. The final amount when the project was completed was 50000.00. The project manager{PM} did not give the contractor  the signage...

View Article


NEC ECC: Final Account time frame.

What is the time frame for  the QS  to complete the final account since final completion has been granted. He had all the information required to complete the final  account. From when are you...

View Article

NEC ECC: Process to implement Clause X1 where no indices have been included?

We are currently working on a JV project which has clause X1 included in the contract documentation. We are aware that indices should be written into contract data part 1 but this has been overlooked,...

View Article

NEC ECS: If the subcontractor includes a risk register as part of his lump...

View Article


NEC ECC: Compensation Event Time Bar Clause 61.3

Under NEC3 ECC, to ensure a change to the Prices, the Completion Date or Key Date, the Contractor was required to ' ... notify a compensation event within eight weeks of becoming aware of the event ......

View Article


NEC ECSC: Can a Compensation Event occur after defects date

We have completed a project under ECSC contract and the defects date has now passed but an event has occurred which would ordinarily be a CE under clause 60.1(14). I appreciate that clause 61.5 states...

View Article

Answered: NEC ECS: Providing grounds for rejecting a nominated Subcontractor

You can reject for any reason - but if that is not a valid reason under the contract then this will be a compensation event. Any increase cost the subcontractor will incur for going elsewhere they can...

View Article

Is the project manager entitled to deduct more advance payment repayment from...

Say the advance payment repayment is pegged at $128 000 per month, can the Project Manager increase this figure to say $220000 and this is done without consultation with the contractor.

View Article

NEC ECC: Management staff costs when assessing delays

How do you assess changes in management? The contract has a site management team which changes during the project. At the start ( 1xProject Manager, 1x Site Agent, 1xWorks Manager, 1xengineer) as per...

View Article


NEC ECC: Cancellation of CE's

There is 3 parts to this question: Option B Contract 1.If a CE was raised up to Part 3 being received from the Contractor, how do you cancel a CE? 2. What if the CE was notified, Part 2 was issued to...

View Article

NEC ECC: Use Option A and Option C Under one Contract

We are proposing to award a contract using Options A & C under one contract.  the materials will be scheduled under the Option A, with the Installation element under the Option C with...

View Article


Answered: NEC ECC: Is a PMI always a Compensation Event?

Examples of PMIs which are not compensation events : - an instruction to attend an early warning meeting (clause 16.2 of NEC3 ECC) - an instruction to remove a person (clause 24.2 of NEC3 ECC) - an...

View Article

Answered: NEC ECC: Project manager not supplying all the information to...

First of all prime cost sums should not be used in NEC. The Works Information should be sufficient to allow the contractor to plan and price his works. In answer to your questions 1) The provision of...

View Article


Answered: NEC ECS: If the subcontractor includes a risk register as part of...

The Risk Register is a project management tool to help all parties deliver the contract. It is not a means of assigning the commercial aspects of the risk. If you are on an Option A and the total of...

View Article

Answered: NEC ECSC: Can a Compensation Event occur after defects date

As you state clause 61.5 sets out that a CE is not notified after the defects date however if both parties are in agreement to have the work carried out then clause 12.3 can be used to record the...

View Article

Answered: NEC ECC: Compensation Event Time Bar Clause 61.3

Good question. I think the obligation is on the Contractor to notified if he believes the matter to be a compensation event so presumably it is within 8 weeks of becoming aware that a matter he...

View Article
Browsing all 3204 articles
Browse latest View live