Answered: NEC ECS: Best way to make a critical path delay claim

$
0
0
Sounds like you are working on a Transport for London / London Underground Project which requires traction current to be discharged to allow works to be undertaken during an Engineering Hours shift.  This is an extremely difficult compensation event to quantify and assess, both in terms of cost and programme, having personally administered literally 1000's of these over the years.

Essentially, however, it is 'just another CE' and the same rules apply here in terms of Defined Cost and programme assessment.  Review each operation (activity) in terms of time, based upon the allowable working time (say 15 mins following traction current switching and 10 mins prior to the Call Back time given.  This gives a 'productive working time' for each Engineering Hours shift.  Then calculate the total amount of time and assess the total programme duration for that operation, or connected series of tasks (not including Time Risk Allowance).  Do this for each operation and see where the critical path 'travels' through.

Not all 'frustrated (cancelled / delayed / disrupted) access' shifts will lead to a delay to planned Completion, although many will incur 'activity prolongation', where you can demonstrate that the duration has increased due to the direct effect of compensation events (from the calculation of total productive working time above).  

Personally I would suggest that the effect is calculated on a Periodic (4 weekly) basis which will require agreement with the Contractor.  This ensures a fair and reasonable assessment, otherwise it is nothing other than guesswork trying to calculate the effect of individual events.  Bear in mind that such an event is most likely a back-to-back entitlement under the main contract anyway and I can likely guarantee that the Contractor is having problems trying to reasonably substantiate his assessment under the main contract, which is probably why the Contractor's administration of this matter is a bit 'hit and miss'.

Your assessment of losing 3 shifts with 3 teams equaling 1 day may sound reasonable but a more detailed and considered approach will take away a large element of subjectivity in the assessment.  I am aware that some activities require a minimum amount of time during an Engineering Hours shift otherwise it cannot be completed, for example; certain 'hot' works, or track or signaling based activities, which can be treated separately as an entire shift may become non-productive where (say) an hour of time is lost.

From what you say, it looks like you are notifying each event so that is a good start and submitting quotes as well, although the programme assessment appears less consistent.  Maybe think about the approach I have suggested above with regard to 'productive working time' and see what the calculation gives you in terms of time.

I appreciate that there are also other risks, including; the loss of time may increase the risk for 'handback', although a generic principle would make things a lot easier to administer and would likely give a fairer solution as not all risk will be realized anyway..