Answered: NEC ECC: Under option D, what happens if a work item is included in the Works Information but was excluded in the Bill of Quantities?

$
0
0
Yes, in accordance with Clause 60.6 the PM should correct the mistake in the BoQ which would be a compensation event (assuming the work item was not covered by the item coverage of the stated BoQ items).