Answered: NEC ECC: Can I claim a lost shift NCE under option A after the Contract Completion date?

$
0
0
Surely if the client is designing the contract on the hoof, that will (a) be a compensation event as they will be adding to and changing the Works Information and (b) causing you delay.

In which case, the original Completion Date should have been going backwards ?

Regardless, it does not actually matter whether you are late achieving Completion or not as if the Employer delays you, it is probably a compensation event and the Completion Date is put back the same amount of time that Completion is delayed by reference to the Accepted Programme.