Surely if the client is designing the contract on the hoof, that will (a) be a compensation event as they will be adding to and changing the Works Information and (b) causing you delay.
In which case, the original Completion Date should have been going backwards ?
Regardless, it does not actually matter whether you are late achieving Completion or not as if the Employer delays you, it is probably a compensation event and the Completion Date is put back the same amount of time that Completion is delayed by reference to the Accepted Programme.
In which case, the original Completion Date should have been going backwards ?
Regardless, it does not actually matter whether you are late achieving Completion or not as if the Employer delays you, it is probably a compensation event and the Completion Date is put back the same amount of time that Completion is delayed by reference to the Accepted Programme.