What piece of paper this is submitted on is irrelevant. As long as it complies with 13.1 and 13.7 (i.e. in writing and separate) then there is nothing to reject here. Anyway, under NEC3 and the ECC, the Project Manager has to make their own assessment of Defined Cost whether the Contractor has submitted an application anyway so again not sure what there is to reject here.
↧