Answered: NEC ECC: Can I retract a programme under option A

$
0
0
The 'client' (Employer) not providing the design on time (as shown in the Accepted Programme) is a compensation event under clause 60.1 (3).  This would entitle you to submit a quotation and a corresponding programme, showing the effect on planned Completion (and Key Dates).  Although you are obliged to mitigate the effects, this does not include accelerative measures so your planned Completion date may not align with the 'client's' expectations.

Contractually the Project Manager would need to instigate the acceleration provisions under clause 36 to achieve Completion by a revised Completion Date.  Note, however, that the Project Manager can instruct a change to a Key Date under clause 14.3, which is a compensation event under 60.1 (4).

It sounds like your submitted programme and quotation may have encompassed both a compensation event AND acceleration measures.  I'm not sure what mechanism was used to request this under the contract, but be careful not to get caught up with 'sloppy' contract administration.

If the submitted programme was part of an instruction for an acceleration quotation, it sounds like the Project Manager hasn't responded and the Project Manager not responding in the period for reply (clause 13.3) would effectively make your submission 'redundant' and require a further instruction to start the process again.  

If the programme was submitted as the regular (4 weekly / monthly) submission, then the lack of response means that the Project Manager has effectively lost the chance to respond and the matter is actually a compensation event under clause 60.1 (6).

I hope that any assumptions I have made are correct.