Answered: NEC ECC: Why can we not claim staff cost for CE's that do not affect critical path?

$
0
0
It sounds as if they are changing the Works Information by introducing extra work.

This involves, from what you say, more people on site for longer. There is therefore - and this is the key thing - a change in Defined Cost. This is therefore assessed in accordance with clause 63.1 i.e. you get the change in Defined Costs + Fee.