We have an option E project where we have omitted £10000 of tendered work, but added in £20000 of work including Fee should the omitted work be the omission plus fee which would effectively reduce the additional cost to the client, my view is that the omission should be 10000 a colleague thinks we may be missing a trick to reduce the defined cost to the client a third party comment would be appreciated?
↧