NEC3 Contract-Can you notify a change to works information compensation event(60.1(1) without a PMI(14.3)

$
0
0
The NECPM is replying to RFI's and providing construction details not shown on the contract drawings(which are works information).
The Contractor considers this is a change to the works information.
Can we notify a compensation event under 60.1(1) even though the NECPM has not issued an instruction under CL14.3.