Answered: NEC ECC: option B re-measure quantity as zero

$
0
0
It would not satisfy the bullet point in 60.4 of rate x FINAL quantity being greater than 0.5% of the Prices are the Contract Date, so the Contractor would not get anything.

This is one of the many flaws with the BoQ clauses 60.4 and 60.5 as written which were not corrected in 4th edition ... a grrrr of frustration !