Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Browsing all 3204 articles
Browse latest View live

Answered: NEC ECC: Breach of Contract and the assessment of CE's

From what you have described, it sounds like an event occured which prevented working for the last hour of each day, which was a CE.  This occured on 12 occasions.  I can see why the effect would be...

View Article


Answered: NEC TSC: Option A - Contractors Risk Allowance

Whenever a Contractor assesses a compensation event - they have to price for the realistic risk that they can see and price for the event as they see it. If you do not have your subcontractor tied into...

View Article


Answered: NEC ECC: Does Cl 65.2 have a limit?

No - once implemented that is it. If it costs a lot more, Contractor could try to claim that was due to other reasons that could be a compensation event but the PM would have to agree that it is indeed...

View Article

Answered: NEC ECC: Roles in termination

Section 9 contains the termination provisions. The procedure and the amount due depend on the reason for termination with reasons stated in clause 91, procedures to be followed in 92 and amount due 93....

View Article

Answered: NEC ECC: option B re-measure quantity as zero

It would not satisfy the bullet point in 60.4 of rate x FINAL quantity being greater than 0.5% of the Prices are the Contract Date, so the Contractor would not get anything. This is one of the many...

View Article


Answered: NEC ECC: Contradiction within Works Information

From your question it appears there is an ambiguity within the contract documents. Labelling the specific section(s) of the Specification as “Not Used” must mean exactly that. If the section(s) is...

View Article

NEC3 Option B - Defined Cost for BoQ rates

There are two items for the disposal of soil in the BoQ. 1 - Acceptable material 2 - Unacceptable material.   The BoQ mainly quantifies all the material as unacceptable however this was tendered at an...

View Article

Answered: NEC ECC: Does the Client PM need to issue a PMI if they accept a CE...

Depends on the reason for a compensation event, but certainly if this is for a change to the Works Information then yes they should - and more importantly why are you the Contractor doing anything...

View Article


Answered: NEC ECC: Disallowed Costs for stand down at Contractor's fault

Looking at the wording of the clause, it refers to 'resources not used to Provide the Works', so the first test is to demonstrate that these reources are not actually Providing the Works.  There may...

View Article


NEC ECC: SCC- Item 44

A hand tool by definition constitutes a tool held in the hand and operated without electricity or other power. It is powered by hand rather than a motor. Based on this definition does this render...

View Article

NEC ECC: Period for reply - when can a CE be notified?

WE have a situation in an Option A contract where we have as Contractor submitted various routine documentation for acceptance, As-built drawings, for example. Now two years later, after Completion but...

View Article

Answered: NEC ECC: Period for reply - when can a CE be notified?

Interesting. I don’t think the PM is correct. The PM's failure to reply in the period for reply (or the period prescribed) is not due to a fault of the Contractor. I do however think he would be right...

View Article

Answered: NEC3 Option B - Defined Cost for BoQ rates

It is not clear from your question what event the CE was notified for, a pricing error by the Contractor is not a reason for a CE. If there is a rate in the BoQ for acceptable then this is the rate...

View Article


NEC ECC: Disallowed Costs for stand down at Contractor's fault

NEC3 ECS Main Option C, with specific reference to 11.2(25) The Contractor has disallowed the Subcontractor's costs for standing time, referencing the above clause and referring to resources and Plant...

View Article

NEC ECC: Does the Client PM need to issue a PMI if they accept a CE...

There are a lot of CEs on our project and each time we notify the PM ticks the box to accept the notification is a compensation event. However he never issues a PMI for the quotation or works. Can he...

View Article


Answered: NEC3 Option B - Defined Cost for BoQ rates

I must admit I do not particularly like the words in 61.4 that states a PM can reject if they consider it has no affect upon Defined Cost - as this can be misused. They should let the quotation...

View Article

Answered: NEC ECC: Period for reply - when can a CE be notified?

A slightly confusing question/situation. 1) If the comments back from the PM are correct all be it late then these would seem to be a defect (something not in accordance with the Works Information) and...

View Article


Answered: NEC ECC: SCC- Item 44

Under NEC2 this category was 'hand tools and hand held power tools' although was changed under NEC3 to 'hand tools not powered by compressed air'. Essentially this category relates to the portability...

View Article

NEC3 Option B - Defined Cost for BoQ rates

There are two items for the disposal of soil in the BoQ. 1 - Acceptable material 2 - Unacceptable material.   The BoQ mainly quantifies all the material as unacceptable however this was tendered at an...

View Article

Answered: NEC ECC: What clause in the Option A can be used in an Early Warning

I think in this instance although it is an event that WILL happen I would notify an early warning so you can highlight the issue and discuss in a meeting what they want to do about it. Alternatively...

View Article
Browsing all 3204 articles
Browse latest View live