A client has received multiple clause 34.1 deferments, in total postponing work for close on 1 yr. Each time the proposed recommencement date given in the instruction has been within 13 weeks but not transpired. This time it is 15+ weeks. When does the recommencement instruction have to be given? - At the same time as the deferment? Under 91.6 some suggest it has to be at the same time otherwise, as here, an Employer can deferment works with impunity in 13 week slices.
↧