The Employer instructs additional work before agreement of the Target Cost and asks the Contractor to provide an accelerated programme to retain the original Completion Date (the Contractor advises that the programme is increased by 14 weeks). The Contractor has provided this by increasing his hours on site, resources on site, i.e. increased site prelims and labour etc. and has increased his prelim (50%) to cover the cost of this but has also omitted his Terminal Float (originally 11.6 weeks) to achieve this Completion Date and has valued the Terminal Float at the accelerated/enhanced weekly prelim charge for the duration of his Terminal Float. Should the accelerated prelim not be the only additional cost?
↧