NEC ECS: Is payment on termination due 13 weeks after notice of termination...

The Contractor gave notice of termination to his Subcontractor, but delayed the certificate of termination by several weeks. In essence, is termination effected for purposes of the final payment, on...

View Article


NEC ECC: Contract not paid suppliers and lost plant/equipment

The Contractor has not paid its suppliers and a plant which was being used to complete the works has gone missing and the Contractor could not explain where its gone. What am I able to do regarding the...

View Article


NEC ECC: specification from Works Information or Bill item

The specification provided by the Architect and included in the Works Information has described and given the type of product to be used in the construction.  Essentially approximately 1,750m2 of a...

View Article

Answered: NEC ECC: (Option C) - What defined costs can the Contractor apply for?

Whatever was included in the Contractor's activity schedule does not define the scope of works, which is essentially defined by the Works Information.  Under a main option C the activity schedule gives...

View Article

Answered: NEC ECC: Which accepted programme is used to measure a CE impact?

This is an area I wrote an article on back in 2013 which you can find in the "guidance/publications" section of my "GMH Planning" website. What I concluded in the article was that NEC3 implies the...

View Article


Answered: NEC3 ECC - Standing down the Contractor.

Termination is a possibility and under NEC3 the Employer has the right to terminate for any reason.  As the Contractor has performed well so far, however, one of the risks is that the works may have to...

View Article

Answered: NEC ECC: Termination & Pain Gain calculation

Yes.  Main Option C adds clauses 93.4 and 93.6 which detail how the share amount is assessed, which is then added (or deducted as the case may be) to the calculated total.

View Article

Answered: NEC ECC Option E: De-scope of work and dead time due to Access

Under option E a Contractor can only claim the costs that they are incurring. If you add work or take work away they should do so as efficiently as possible knowing that disallowed costs could be...

View Article


Answered: NEC ECS: Is payment on termination due 13 weeks after notice of...

It must be when the termination certificate has been issued, as various actions, including the Subcontractor being obliged to stop work, commence when this has occurred.  Note that the ECS contract...

View Article


NEC ECS: Disclosure requirement of subcontractor costs for compensation...

We have a NEC3 ECC Option A contract (or a NEC3 based contract because of many amendments), My question is: Are we obliged to show the employer our subcontractor offers (unit rates) in case the...

View Article

Answered: ECC Main Option A and Inflation under Compensation Events

In short 'Yes', as the compensation event will have affected Defined Costs. Consequently, the Contractor is entitled to those changes in Defined Costs which are due to "the effect of the compensation...

View Article

Answered: NEC ECC: how does PM assess a late CE

When you say submit, it depends on what part of the CE process you are talking about. They should notify the CE within 8 weeks otherwise they are time-barred - assuming it is one of the ones they are...

View Article

NEC ECC: Option C - Off Site Fabrication - Sub-Contract Fee or Direct Fee?

If a Contractor under an Option C issues an NEC3 Supply Contract for some off site fabrication does this attract the sub-contract fee % or the direct fee % in their applications?

View Article


Answered: NEC ECC: Contract not paid suppliers and lost plant/equipment

In your question you state plant by which I assume you mean Equipment. You don't say if your concerns extend to the Contractor not performing on site progressing the works. I suggest that if the...

View Article

Answered: NEC ECC: Non-payment for Subcontract within the working area

Under a Main Option E, costs are either 'disallowed' because they do not comply with the category requirements in the Schedule of Cost Components, the definition of Defined Cost or they are a...

View Article


Answered: NEC ECS: What is the procedure if the Contractor has neither...

You have to notify the fact that they have not responded to your notification (in writing, separately from other communications) in accordance with clause 61.4. If they are silent for a further three...

View Article

Answered: NEC ECC: Payment for Attendance at Subcontractor Works

Under NEC3, to be treated as a 'genuine' cost, People costs are required to be incurred in order to Provide the Works and also be within the Working Areas.  In this instance the premises was not in the...

View Article


NEC ECC - can terminal float be purchased from a Contractor for Target Cost...

The Employer instructs additional work before agreement of the Target Cost and asks the Contractor to provide an accelerated programme to retain the original Completion Date (the Contractor advises...

View Article

Answered: NEC ECC - can terminal float be purchased from a Contractor for...

Anything goes before the contract is signed! If this is the Contractor's offer that they will increase the Prices (target) by X in order to maintain the original Completion Date and that is...

View Article

NEC ECS: Using X18 to limit X7 delay damages?

Included within an NEC3 Option A subcontract agreement, the Subcontract Data under X18 states: 'The Subcontractor’s total liability to the Contractor for delay allowable under this contract is limited...

View Article