NEC ECS: Using X18 to limit X7 delay damages?

$
0
0
Included within an NEC3 Option A subcontract agreement, the Subcontract Data under X18 states:
'The Subcontractor’s total liability to the Contractor for delay allowable under this contract is limited to; 10% of the total of the Prices.'

However as delay damages are an excluded matter will X7 delay damages sit outside of the 10% cap?