Answered: NEC3 ECC: X5 & 7 - Damages that Contractor would incur

$
0
0
There are two elements to this question:
Firstly and quite subtly there are different financial liabilities for missing a sectional completion rather than a Key Date. If a sectional or the overall Completion Date is not achieved for reasons that are the Contractors liability then they will be liable for the (fixed) damages outlined in X7 (contract data part 1). However, if a Key Date is missed due to the Contractors fault then clause 25.3 states that any cost incurred by the Employer as a result (on the same project)  will be recoverable from the Contractor. These are undefined costs from the outset so could be a big risk to the Contractor compared to delay damages which are at least ascertained.

The second part is easy. You can claim back from the Subcontractor what ever your contract allows between you and your Subcontractor. If you have put in a sectional completion or a Key Date in their contract that they fail to meet for reasons that are their risk then you can use 25.3 or X7 accordingly. If you haven't then I fail to see how they can be in breach of contract and section 8 of the contract will not help you.

Viewing all articles
Browse latest Browse all 3204

Trending Articles