NEC3 ECS: Where does the Schedule of Cost Components sit

$
0
0
Very new to NEC Contracts!

Where does the schedule of cost components usually sit in an Option A Subcontract? I have started a new role recently and there are several Option A Subcontracts on jobs I have inherited.

On one of the contracts the subcontractor has quoted a CE using among other things some rates for various operatives.

I would have expected to see such rates on a schedule of cost components and I assumed that would be located in Contract Data Part Two.

Contract Data Part Two of the proformas I am using has been "customised" by the contractor I am working for and contains no such rates. Is this where they would normally sit?

Many thanks in advance.