Provided appropriate access was given in order to correct the Defect, then the PM can take action under clause 45 following the expiry of the appropriate defects correction period.
To initiate discussion, the PM could assess the cost of having the Defect corrected by other people and communicate this information to the Contractor, prior to taking any further action.
To initiate discussion, the PM could assess the cost of having the Defect corrected by other people and communicate this information to the Contractor, prior to taking any further action.