Answered: NEC ECC: When is the Contractor entitled to a direct fee and when is a subcontractor entitled to a Subcontractor's fee?

$
0
0
Just to add to QS007's comment above, As well as including for P&G type costs, the direct fee also includes head office overheads and any other cost not included in the Schedules of Cost Components.