NEC ECC: If the Project Manager accepts a Project programme and the Planned Dates are later than the Contract Dates what is the client accepting?

$
0
0
When the Project Manager (Client) accepts a project programme submission what are they accepting in terms of dates? If the submission states Planned Dates that are later then the Contract Dates is the client agreeing to new Contract Dates?
What is the client accepting?
Can the client not accept if the Contract Dates are not being met?
This is a recurring situation that I come across with some on one side of the argument and some on the other. Clarification would help.