No, because:
- the changes to the Accepted Programme can cover a multitude of things mainly, I would argue from the Contractor having had time to look in detail at stuff in Stage 1. That changes sequences, timings etc.
- it does not specifically mention a change to the Completion Date.
Note that other clauses in X22.3 or the notice to to proceed to Stage 2 - as per clause X22.5 (1) - does not change the Completion Date either.
- the changes to the Accepted Programme can cover a multitude of things mainly, I would argue from the Contractor having had time to look in detail at stuff in Stage 1. That changes sequences, timings etc.
- it does not specifically mention a change to the Completion Date.
Note that other clauses in X22.3 or the notice to to proceed to Stage 2 - as per clause X22.5 (1) - does not change the Completion Date either.