Answered: NEC ECC: Defect not spotted immediately

$
0
0
Sorry but it is your obligation to provide the works in accordance with the Works Information. You are obliged to correct your defects. The fact it will cost you a lot more to correct is still your problem. Their acceptance does not change your liability to provide the works in accordance with the Works Information.

The only other option is by proposing not to correct the defect and offering a saving (see clause 44) but they are under no obligation to have to accept your offer of a saving.