Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Viewing all articles
Browse latest Browse all 3204

NEC ECC: Accepting the correction of a Defect

$
0
0
What is the standard practice of accepting the correction of a Defect under the NEC?

Under the contract the Supervisor issues a Defect Certificate as per clause 43.3 at the end of last defect correction period however rather than wait until end of project we are looking to get defects signed off as accepted along the way (rather than wait until the end)

Would this just be a simple template were the Supervisor signs off the defect to say he is satisfied it has been corrected? Can not find anything within the NEC contracts with regards to signing off a defect as accepted.

Viewing all articles
Browse latest Browse all 3204

Trending Articles