NEC ECS: Correcting a defect we know the end Client has accepted

$
0
0
We are a Subcontractor under an NEC3 Option C.

We have been asked by the Contractor to provide a quotation indicating the time/cost saving for accepting a Defect.

We are aware that the ultimate client has accepted the Defect and permitted a concession (we have documented proof of this).

Can the Contractor still request the quotation even though the decision to allow the Defect to remain uncorrected has already been made?