We are a Subcontractor under an NEC3 Option C.
We have been asked by the Contractor to provide a quotation indicating the time/cost saving for accepting a Defect.
We are aware that the ultimate client has accepted the Defect and permitted a concession (we have documented proof of this).
Can the Contractor still request the quotation even though the decision to allow the Defect to remain uncorrected has already been made?