Answered: NEC PSC - Not delivered full scope

$
0
0
If for some reason they can not provide all of the Scope that they were due to provide, then you should give them (have given them) an instruction to not do that element of work. Yes this would then be a compensation event and you should request them for a quotation (for the saving). They should then asses the cost that the work would have cost them to do - less any cost that they have already occurred for that element of works (if any). They cant just say it wasn't their fault the work was not able to be done and claim that the Prices (i.e. option C target) should not move.