I have a query regarding an Option A contract (poorly written as it has elements of Option C within it).
CD Part II states the Direct Fee, Subcontracted Fee, People Overhead % and Working Area Overhead % which have all been populated.
Normally, an Option A would use the SSCC to calculate CE's. However, the client has used it's own "Schedule of Cost Components" which looks in comparison like the full schedule.
The Client is now querying why i've used the WAO percentage as this is not used in Option A.
Does the normal rules apply or do i just say that the contract states that Fee is to be applied to the defined cost schedule provided by the Client and in the contract, based on the percentages in the Subcontract Data?
CD Part II states the Direct Fee, Subcontracted Fee, People Overhead % and Working Area Overhead % which have all been populated.
Normally, an Option A would use the SSCC to calculate CE's. However, the client has used it's own "Schedule of Cost Components" which looks in comparison like the full schedule.
The Client is now querying why i've used the WAO percentage as this is not used in Option A.
Does the normal rules apply or do i just say that the contract states that Fee is to be applied to the defined cost schedule provided by the Client and in the contract, based on the percentages in the Subcontract Data?