Answered: NEC4 ECC: Appendix 5 Example tender assessment sheet

$
0
0
The NEC4 example makes the appropriate adjustments as there is now no People Overhead, Design overhead and only a single Fee applied.

It does look, however, like the calculation for item 4 should be A x B x G, which is the Client's estimate of 12% difference.

The guidance notes do contain a number of errors.so care should be taken to validate any specific information.