Contractor's QS has applied for QS and PM time for preparing the Compensation Event, from what I have read in the NEC4 Option C contract its ambiguous. My understanding is that this is part of the defined cost, Hence already included within the prelims and change control is a large part of the QS role. Am I correct is saying it should not be an allowable claim?
↧