Answered: NEC ECC: No work on programme

$
0
0
No the Client  can not "insist" as it is your programme and your prerogative as to how you do the works efficiently for yourself whilst meeting any contractual deadlines. They may question why you wouldn't, but you would assume you have your reasons otherwise surely you would.