NEC ECS: Defects period and the Coronavirus impact

$
0
0
NEC3 ECS Main Option C, D and E.

Where defects are concerned after Completion, a number of projects are currently in the defects period, of which a couple have defects raised to be dealt with by the Subcontractor.

In light of the coronavirus situation, would a prevention compensation event under 60.1.19 be applicable during the defects period for existing known defects? and likewise if any new defects are identified in the future during the defects period?