Quantcast
Channel: ReachBack by BuiltIntelligence - Recent questions and answers in NEC3 and NEC4 Contracts
Browsing all 3204 articles
Browse latest View live

Answered: NEC ECC: Equipment Minimum Hire Period and CECA

You should be able to claim the cost that you have incurred as a result of that compensation event. If you can demonstrate that it was on a minimum one week hire then that is what should be assessed as...

View Article


Answered: NEC ECC: Compensation Events and Utilisation of Resources on Site

Under clause 63.3 (NEC3 ECC) or clause 63.5 (NEC4 ECC) if, due to the compensation event, there is no effect on planned Completion compared with that in the Accepted Programme, then there is no change...

View Article


NEC ECC: Evaluation of an omission via a compensation event

Contract NEC3 ECC Option B On one of our projects the designers have revised the drainage during the contract period. The contractor has assessed the compensation event using defined cost and in doing...

View Article

Answered: NEC ECC: Medical Suspension - Disallowed Costs?

Assuming we're talking about a person employed by the Contractor then the Employer does have some liability to pay for people who are absent due to ill health. The Schedule of Cost Components item...

View Article

Answered: NEC ECC: Is the Contractor obliged to notify sub-subcontractors to...

No, not unless there is a Z clause that specifically requires this. The unamended ECC defines a Subcontractor as someone who has a contract with the Contractor. A Subsubcontractor in an ECS does not...

View Article


NEC ECC: Acceptance of CE quotation and subsequent realisation it was not a CE!

Contractor issued EWN related to ground conditions. PM requested a quotation which was submitted by Contractor and subsequently accepted by the PM. Following a review by the Clients team, it was found...

View Article

NEC ECC: Acceptance of Programme and Delay in Progress Onsite

The Contractor on our project have recently submitted their next programme for acceptance. The programme is dated the 28 February but was not formally submitted to the Project Manager for acceptance...

View Article

NEC PSC: Responsibility of planning discharges

We are working on an NEC Option A contract with novated design consultants who are novated through a professional services agreement. The Employers Agent and the novated consultants are from the same...

View Article


Answered: NEC ECC: Acceptance of Programme and Delay in Progress Onsite

It all depends on the “data date” of the programme, i.e. the date they have rescheduled the programme to. If they have issued the programme on the 11th March but it was for progress up until the data...

View Article


NEC ECC: Coronavirus protocols is determining that non construction staff...

I under an NEC3 (Option C) contract, if a project agreed that non essential project personnel were to work from home, how could the ‘defined site’ be adjusted to accommodate home workers in exceptional...

View Article

NEC: Which CE would delays due to Coronavirus be?

Under NEC4 would CE number would we use for notifying the client of time and cost implications relating to Coronavirus?

View Article

NEC: Coronavirus what are the contractual implication with the NEC?

With the current impact of the Coronavirus what are the contractual implications if work on site is delayed through it impacting the contractor supply chain?

View Article

Answered: NEC: Coronavirus what are the contractual implication with the NEC?

Much has been written about 'prevention events' and whether work is impacted such that it is not reasonably possible to complete on time. However, for any contracts entered into prior to the outbreak...

View Article


Answered: NEC: Which CE would delays due to Coronavirus be?

If you have X2, Changes in the law in your contract, I would notify under that as (to quote my colleague Andrew W-I: "In response to the COVID-19 outbreak, the United Kingdom Parliament enacted a...

View Article

Answered: NEC ECC: Coronavirus protocols is determining that non construction...

Working from home is already covered in the Schedule of Cost Components and Working Areas wouldn't necessarily need to be extended to include everyone's home addresses. Under the Schedule of Cost...

View Article


Answered: NEC PSC: Responsibility of planning discharges

You need to keep contractual lines of responsibility clear and distinct from each other. Firstly, what are your obligations to the Employer in respect of planning conditions? If you have any they...

View Article

Answered: NEC ECC: Acceptance of CE quotation and subsequent realisation it...

Clause 65.2 states that an assessment of a compensation event is not revised if a forecast upon which it is based is shown by later recorded information to have been wrong. The clause specifically...

View Article


Coronavirus - contractual implications

With the potential issues created by Coronavirus what are the contractual implications if work on site is delayed. Notwithstanding X2, is NEC3 ECC Cl 60.1 (19) applicable, is the virus deemed a force...

View Article

Answered: NEC ECC: Coronavirus - contractual implications

See my colleague Jon Broome's answer using this link:https://reachback.builtintelligence.com/18883/nec-which-ce-would-delays-due-to-coronavirus-be

View Article

NEC ECS: Defects period and the Coronavirus impact

NEC3 ECS Main Option C, D and E. Where defects are concerned after Completion, a number of projects are currently in the defects period, of which a couple have defects raised to be dealt with by the...

View Article
Browsing all 3204 articles
Browse latest View live