NEC ECC: Accepted programme

$
0
0
Am I correct then in assuming that if the PM accepts a programme (cl32) with a planned Completion delayed by 1 wk due to the notified CE (unaccepted) of a 2wks duration the Completion Date is unaffected.

Thus when the PM assesses the CE  at 1wks duration, planned Completion will be the same as the completion date thus no change to the project Completion date.