Answered: NEC ECC: Compensation Event Retrospective Claim

$
0
0
The amendments to NEC4 2019 version finally put in words what I believe they always intended. You take the last Accepted Programme, but first bring it up to date with progress and other compensation events that had already happened prior to the new compensation event coming along (called the "dividing date" in NEC4).  You prove where you were before the CE came along (or attempt to prove) and then see the extra over effect the new CE has genuinely had, if any, on planned Completion (or sectional/key dates).

The wording of NEC4 recognises that you cant put a new CE into a programme that is say four months old (last accepted) and expect to get a correct or fair result to either party.

This principle was always the intended one so for me still valid for NEC3, just made clearer in NEC4.

Viewing all articles
Browse latest Browse all 3204

Trending Articles