I'm working with a NEC3 ECS Option B. The subcontractor has forgotten to provide a rate for specific item of works that was stated on the BoQ to be priced for (the line item and quants are in the BoQ, just no rate given).
They are now applying for those works as they are carrying them out. Is it possible to add in the rate that was missed out of the BoQ into the contract? or could we add in the item of work that was missed as a Day rate into the contract? Thanks.