I'm working with a NEC3 ECS Option B. The subcontractor has forgotten to provide a rate for specific item of works that was stated on the BoQ to be priced for (the description of the item and its quants are in the BoQ, they just didn't put a rate).
They are now applying for those works as they are carrying them out. Is it possible to add in the rate that was missed out of the BoQ into the contract? or could we add in the item of work that was missed as a Day rate into the contract?
Because right now i feel the only way for them to charge for the work is via a CE however i don't believe there is a clause they could even use because they're not doing additional works and we haven't changed the scope of works for them either.
They are now applying for those works as they are carrying them out. Is it possible to add in the rate that was missed out of the BoQ into the contract? or could we add in the item of work that was missed as a Day rate into the contract?
Because right now i feel the only way for them to charge for the work is via a CE however i don't believe there is a clause they could even use because they're not doing additional works and we haven't changed the scope of works for them either.