I am facing a scenario under Option A NEC3 contract where the PM requested a quotation under clause 61.2. for additional work.
The contractor submitted his quotation which the PM assessed but to a lesser amount than that which the contractor quoted.
I assume the contractor now has to carry out the additional work and if he disputes the assessment he must follow the dispute resolution route.
The contractor submitted his quotation which the PM assessed but to a lesser amount than that which the contractor quoted.
I assume the contractor now has to carry out the additional work and if he disputes the assessment he must follow the dispute resolution route.