Under clause 50.1 'Later assessment dates' occur at the end of each assessment interval until 4 weeks after the Defects Certificate is issued and at Completion. If Completion and the corresponding assessment occur part way through an assessment interval, am I right in assuming that the assessment interval starts again from the assessment made at Completion? E.g. if the assessment interval is 4 weeks and Completion occurs 2 weeks into the assessment interval triggering an assessment then presumably the subsequent assessment will occur after a further 4 weeks not a further 2 weeks?
↧