NEC3 ECC: Where the specification is to be confirmed

$
0
0
An item in our scope of works at tender stage stated "TBC", due to the lack of detail the estimators did not price this item , subsequently the Construction drawings now provide a full detailed spec, is the Contractor allowed to claimed the full defined cost associated with this item or should an allowance been made at tender stage? What is the best approach in dealing with such change?