It is the difference between the 1 in 10 value and the actual data. The compensation event should then assess the impact of this extra days rain as to what it had in terms of time and cost. In practice this is usually very difficult/subjective to definitively determine the specific impact of this one day - but that is what the Parties have to try to determine.
↧