Answered: NEC3 ECC: Option B - Cancellation of Work Order booking - Lost labour resource as a result?

$
0
0
Any such items would be assessed as a compensation events - which would generally be calculated using Defined Cost (shorter schedule of cost components) rather than a pre-determined rate within BofQ. The time and cost effects of the compensation event would be assessed in terms of how it has affected planned Completion.