NEC3 ECC: SSCC - Charge 41 Application

$
0
0
Is it intended that Equipment e.g. fuel bowser, generator, and indeed fuel for generators required to provide electricity to the Working Areas (site compound which has been included in the Working Areas), would be covered under Charge 41 of the Shorter Schedule of Cost Components?

If the Contractor had connected to mains supplies then the utility bills would surely be covered by the first bullet point, if they are running from temporary generators then is it fair to assume that the "provision and use" includes these items as without them it would be impossible to provide and use electricty?