The simple answer is no, and I'm not aware that NEC has an official position on this either.
Personally I amend secondary Option X19: Task Order by Z clause to use this for all unplanned / reactive / emergency / minor works. Others chose to include a procedure in the Service Information.
I wouldn't advocate doing anything retrospectively as it doesn't help you manage the contract or your budgets.
Personally I amend secondary Option X19: Task Order by Z clause to use this for all unplanned / reactive / emergency / minor works. Others chose to include a procedure in the Service Information.
I wouldn't advocate doing anything retrospectively as it doesn't help you manage the contract or your budgets.