Answered: Creating Float on the Critical Path

$
0
0
if your are able to advance planned Completion through better performance reprogramming etc then the gap produced between this earlier date and the Completion Date is "terminal float" and belongs to the Contractor (presuming that planned completion is earlier then the Completion Date).