We are currently in dispute with the Contractor regarding how a CE should be assessed under the NEC3 Short Form. The client has insisted on a Bill of Quantities being included . We have instructed the omission of an item under 60.1.1 which omits an element of the work. The QS views this as a simple re-measurement under 63.1 whilst the Contractor insists this should be assessed under 63.2 due to the his work sequence/ methodology being affected. How should this be assessed?
↧