NEC3 ECS: Which clause should a Subcontractor claim under when issueing an NCE for disruption

$
0
0
The Contractor has also instructed the Subcontractor to ramp up and significantly increase its workforce however the only areas that the Contractor has made available to the Subcontractor are incomplete and unchecked.

The Subcontractor has limited areas available to lay his cables and completes significantly less works every day than he would normally expect. In addition the Subcontractor cannot combine activities i.e. he cannot complete 4 installations per day as the only installations available a too far apart to be combined.

The Subcontractor wishes to issue an NCE as he believes he has been disrupted by the Contractor.

Which clause should the Subcontractor refer to within the NCE as there is no disruption clause under the NCE process.