Answered: NEC3 ECS: Which clause should a Subcontractor claim under when issueing an NCE for disruption

$
0
0
As Dave says - you cant claim for general disruption or prolongation. You need to ascertain what event caused your planned Completion to move, and notify under one of the reasons within clause 60.1 that that thing was a compensation event. Once agreed it is one, you can produce a quotation which would include prelim type costs for planned Completion moving.