Answered: NEC ECSC: Who runs risk of items missed off the Price List?

$
0
0
The Contractor's obligation is to Provide the Works in accordance with the Works Information, not in accordance with the Price List therefore how the Contractor prices the Price List would usually be a Contractor's risk. If you review the compensation events under clause 60.1 there isn't one for work being required that isn't included in the Price List and as such there would be no compensation event for the Employer insisting that the Contractor does the work that the Works Information requires him to do. This work is deemed included in the Price List even if there isn't a specific price for it.