Pragmatically I would seek to agree a contract amendment between the Employer and Contractor to clarify what was meant. You would either need to amend the weather measurement so that it fits with the Met Office data or maybe add an additional compensation event along the lines of "wind speed measured at the crane jib exceeds x for more than y hours per day". The amendment should reflect what the Parties thought the risk profile was at contract award.
↧